The End

Dig a probe under Roman material and what do you find? Yellow bricks of course.

The probe in Grid 32

The probe in Grid 32

Excavation is done. Now, the cleanup begins. So, to Shimi, Ben, Kate, Meghan, and Jeff, congratulations on a job well done. Grid 32 proved to be endlessly fascinating.  This salvage excavation leaves us with a lot to think about over the winter as we start planing the 2015 season. 

Who's ready to get in the dirt?

Grid 32

Grid 32

That's a wrap, everyone.

 

Long Day

Shimi tells me it was a 6:00 am - 5:00 pm day in the field today.  Stratigraphically, they have moved into the Hellenistic/Early Roman period. The plan is to dig a small probe tomorrow to see if there is any differentiation between that earlier material and the Roman/Byzantine period structure they've largely finished excavating.  

The team sent along pictures of several interesting finds:

Fibula

Fibula

Unguentarium

Unguentarium

Finally, Jeff has returned to Ashkelon and he sent along some pictures. This one is of Shimi with Jacob and Uri, two members of the team of Israeli workers. They worked with Shimi during the summer field season before things were cut short and then resumed working with him this month.  Along with the entire team of workers, they did a great job moving a lot of dirt. It goes without saying, work in Grid 32 has made a major contribution to what we know about the site of ancient Ashkelon.

Shimi, Uri and Jacob

Shimi, Uri and Jacob




Rainy Day

It was a quiet day in Ashkelon. Rain kept the workers away.

Puddles in Grid 32

Puddles in Grid 32

One of the benefits of rain, which is generally not an archaeologist's best friend, is that it helps colors/soil changes to really pop. 

"Clean" dirt

"Clean" dirt

Here is a view to the north. It's easy to see the large cut in section ending at the cut portion of wall U66 at left. This may have been to clear rubble before installation of the cistern. The cistern is the installation at the top of the picture (look for the empty sandbags).

Shimi tells me they've asked for workers Sunday and Monday. Check back next week for one last update.

Work continues

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Another day, a lot more dirt moved.

The crew at work.

The crew at work.

As work continues, the "tabun" gets more and more interesting and its identification as such no longer seems certain.

Amphora inside installation

Amphora inside installation

The search continues for a preserved surface.  So far, the best evidence for anything that can be associated with a surface is in the picture below.  Shimi tells me, the white "lump" protruding from the top course of the lower wall is s surface bedding meeting the wall.

Surface bedding running up to wall

Surface bedding running up to wall

Two more days of digging to go.  

Destruction Layer

Today, Shimi and crew dismantled walls as they continued excavating. There is still much to do to reach the required 4 meter depth by the end of the week.

Taking down wall segments

Taking down wall segments

As they continue to excavate, the team is finding greater quantities of ash and indications they might be hitting a layer of destruction debris. Unfortunately, there is still no sign of a floor.

It's not all heavy work all the time, however. Kate pulled a double cleaning some of the painted plaster on one of the wall fragments.

Cleaning some painted plaster

Cleaning some painted plaster

What about the date of this building? Right now, all the evidence points towards the Byzantine period. With any luck, the stratigraphy will allow for a firm date when work is finished.

Only three more days of digging and then the countdown to the 2015 field season begins.

Small Finds

Shimi, Ben and crew have been busy in Ashkelon. This week saw Shimi and Ben power through more than 40 buckets of pottery.  There's nothing like digging it up and cleaning it too!

Pottery laid out to dry

Pottery laid out to dry

They had a number of interesting small finds this week including a glass base, likely from the Roman or Byzantine period, and a jar fragment incised with three letters.

Glass base

Glass base

Jar fragment

Jar fragment

Small finds aren't all they're finding, either. I'll do another post in the next few days showing some photos of the architecture/stratigraphy they are uncovering.  As suspected, digging near the cardo has proven to be very interesting.

With only one more week of excavation -- and 1.25 to 1.5 meters -- there is still a long way to go. Watching the progress over the next few days promises to be very exciting.

Excavation Continues

Shimi, Ben and the crew of workers continue to make significant progress in the salvage excavation.  With 5 days left, they are racing to complete the project so that the Park Authority can continue with its infrastructure improvements. As always, the workers display an enviable ability to multitask.

When work was stopped in early July, the rubble in the middle of the picture above was just being exposed. Even then it was surprising and interesting: pieces of plastered ashlar blocks, piles of floor tiles, and lots of nails.  Of particular interest was the fact that the stones were simply left where they were and covered over.  It's rare that such great building material was, in essence, ignored. 

The resumption of work has revealed even more of this rubble including colorful patterned mosaic fragments, coins, nails, marble veneers and moldings, ashlars and lots of mortar fragments.

Painted plaster on wall fragment

Painted plaster on wall fragment

There is still much to learn about this area and the structure being uncovered. I anticipate we'll know more in the next few days. Hopefully, we'll have an update before it is all said and done. I, for one, can't wait to learn more.

We Are Back in the Trenches!

We have a team back in the field for the next three weeks as we race to stay ahead of the winter rains. The main focus of attention is Grid 32, the salvage excavation project, where Shimi and a crew of hired workers are continuing their excavation of Byzantine and Islamic period occupation levels.

Cleaning up Grid 32

Cleaning up Grid 32

Once excavation is completed, this area will be turned over to the park for the installation of a large pump which is part of a major sewer upgrade for the park.

Shimi -- happy and back in the dirt after passing his comprehensive exams

Shimi -- happy and back in the dirt after passing his comprehensive exams

There is also a little cleaning to do in Grid 51.

Ben in Grid 51

Ben in Grid 51

I'll try to post regular updates the next few weeks while work continues...and even when it doesn't. A rain delay had people scrambling to improvise work spaces.

Co-director Daniel Master waiting out the rain

Co-director Daniel Master waiting out the rain

One More Day

The cancellation of flights in and out of Israel on American carriers means that the dig season goes on a little longer.  This morning we were back in the courtyard of the Albright sorting objects to be sent to restoration, drawing, photography and storage.  We also spent some time talking over the latest events with Matt Adams.  

We are all in agreement -- no one can remember a season quite like this one.

Ashkelon-Megiddo Dinner

Last night the staff and volunteers who spent their last week at Megiddo enjoyed a nice evening out in Tel Aviv.

Dinner in Tel Aviv

Dinner in Tel Aviv

After dinner, the staff returned to Jerusalem where work resumed this morning at the Albright.  Meghan achieved a great milestone today -- she finished the inventory of the Vault.  What does this mean?  It means that we can now move out of the Lab and hand the keys over to our landlord who is already eagerly looking for new renters.  With the Lab closing, tomorrow will see the first trip to the post office as we work on shipping items back to Wheaton and Harvard.

Our remote season shut down continues to go smoothly.  Books are done, computers and hard drives are almost all backed-up, plans are in the work to bring a team back in October to finish the salvage excavation and staff members still here are turning their attention to the various Ashkelon research projects for which they are responsible.